  • TRAFFORD ROAD WORKS NEAR COMPLETION WITH OVERNIGHT RESURFACING TO BEGIN 


    Carl Davison - Editor
     Share

    Salford News



     A £20m scheme to transform the A5063 Trafford Road is edging closer to completion with overnight resurfacing work to begin later this month.
     
    The major route, which connects the M602 Roundabout to The Quays and Trafford, is currently undergoing a transformation with each junction along the route being improved to boost capacity for all users, assist turning traffic and make it safer and easier for cyclists and pedestrians to use.
     
    Now in its final stages, overnight resurfacing work will begin from The Quays to the M602 roundabout from Tuesday 23 August. This work will be carried out in three stages and is expected to last until Saturday 22 October.
     
    Councillor Mike McCusker, lead member for planning, transport and sustainable development said:

    Quote

    “Trafford Road is the biggest road scheme that we have underway and is set to be transformative for residents, cyclists and motorists when we expect it to reopen in the coming months.
     
    “I am delighted that the scheme is moving to resurfacing work towards the M602 roundabout as it shows we are nearing the completion of this project and I would ask residents, businesses and commuters to continue exercising their utmost patience with us as we enter this new phase of the works.
     
    “We are doing all we can to minimise disruption by carrying out this work at night so we don’t fully close roads during the day and ensuring that, where possible, the noisiest work does not take place overnight."

     
    Works will start at 7pm, although residents will see traffic management measures being put in place from 6.30pm. Only one side of the carriageway from The Quays to the M602 roundabout will be closed at a time. The road will reopen to traffic at 6.30am each morning.
     
    This schedule is also subject to change in the event of adverse weather conditions or other issues. Residents will receive further communications in the event of a delay.
     
    Residents can find out more information about the works and talk to our contractor, Sisk, about what it will mean for them at two public information events this month, with one in person and the other taking place online.

    •    Wednesday 10 August, Salford Lads Club, Coronation Street, Salford, M5 3SA - 4pm to 6pm
    •    Tuesday 16 August, online via Microsoft Teams – link here.
     
    Those accessing the online meeting should note that Internet Explorer, Firefox and Safari do not support Microsoft Teams so they will need to download the Microsoft Teams app before attempting to join the session. Microsoft Teams is supported by users who use Chrome or Edge as their browser. Those using a mobile device will also need to download the app onto their device before joining.

     




     Share


    User Feedback

    Recommended Comments

    There are no comments to display.



    Create an account or sign in to comment

    You need to be a member in order to leave a comment

    Create an account

    Sign up for a new account in our community. It's easy!

    Register a new account

    Sign in

    Already have an account? Sign in here.

    Sign In Now

  • Our Facebook Groups

  • Our Facebook Groups

  • Latest Review

  • Upcoming Local Events

    No upcoming events found
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.

Our Privacy Policy, community Guidelines and website Terms of Use can be found on the links provided.